SUBCONTRACT

 

On ___ day of ____________, 20 ____, ________________________,

henceforth "Contractor" and ____________________________,

henceforth "Subcontractor", HEREBY ENTER into the following

subcontract:

 

WITNESSETH:

 

WHEREAS Contractor has entered into, or will hereafter enter into,

a general construction contract, henceforth "The Prime Contract"

with:

_________________ (Owner or General Contractor), to perform in

accordance

with various contract documents and specifications certain work

prepared

by: ________________, henceforth "Architect", and/or to furnish

labor, materials, supplies, labor and/or goods required to

construct the following named and described construction project:

 

_____________________________, henceforth "The Project", located

in ______county, at ___________________ address, and

 

WHEREAS Contractor desires to retain Subcontractor to perform

certain contract work in accordance with various contract

documents and specifications and/or to furnish labor, materials,

supplies, labor and/or goods for The Project;

 

NOW THEREFORE Contractor and Subcontractor agree as follows:

 

ARTICLE I.

SUBCONTRACT WORK

 

1.1 Subcontractor shall be employed as an independent contractor

and shall provide and furnish all labor, materials, tools,

supplies, equipment, services, facilities, supervision, and

administration necessary for the proper and complete performance

and acceptance of the following portions of the work, hereinafter

"the Subcontract Work", for the Project, together with such other

portions of the drawings, specifications and addendum as related

thereto:

 

SEE EXHIBIT A: Scope, Conditions, And List of Attachments

 

ARTICLE II.

SUBCONTRACTOR PRICE

 

2.1 In consideration of Subcontractor's performance of this

Subcontract, and at the times and subject to the terms and

conditions hereinafter set forth, Contractor shall pay to

Subcontractor the total sum of ____________ dollars ($000,000.00),

hereinafter "subcontract price." Said subcontract price is

dependant upon the conditions set forth in Exhibit A being met.

Should said conditions not be met, the subcontract amount shall be

modified accordingly.

 

ARTICLE III.

SPECIAL CONDITIONS

 

The Special Conditions to Subcontract (Articles I through XXI) are

incorporated in this Subcontract as though fully set forth herein. 

Subcontractor hereby acknowledges receipt of the Special

Conditions.

 

ARTICLE IV

COMMUNICATION AND NOTICE

 

4.1 All communications between Subcontractor and General

Contractor, Owner or Architect shall be via Contractor.

 

4.2 Subcontractor shall furnish Contractor with periodic progress

reports as required by Contractor, including status of material,

equipment, manpower and submittal.

 

4.3 Subcontractor shall be deemed to have received notice of a

fact, request, order, or demand when its Superintendent is

notified, either orally or in writing, or three (3) days after

written notice is sent by registered or certified mail addressed

to Subcontractor's last known place of business, whichever is

sooner.

 

4.4 Contractor shall be deemed to have received notice of a fact,

request, or demand three (3) days after written notice is sent by

registered or certified mail addressed to the following address:

 

(Contractor's address)

 

ARTICLE V

GOVERNING LAW AND RULES OF CONSTRUCTION

 

5.1 The validity, interpretation, and performance of this

Subcontract shall be governed by the laws of the jurisdiction

where The Project is located.

 

5.2 Titles, captions, or headings to any provision, article, etc.,

shall not limit the full contents of the same. These articles have

the full force and effect as if no titles existed.

 

5.3 If any term or provision of this Subcontract is determined to

be invalid, it shall not affect the validity and enforcement of

the remaining terms and provisions of this Subcontract.

 

5.4 This contract shall be binding upon and inure to the benefit

of the respective successors, assigns, representatives, and heirs

of the parties herein.

 

ARTICLE VI

AMENDMENT

 

6.1 This Subcontract shall only be amended or modified by written

document executed by authorized representatives of Contractor and

Subcontractor.  This Subcontract supersedes all prior

representations made by Contractor.

 

ARTICLE VII

ARBITRATION

 

7.1 Any and all disputes or claims between the Contractor and the

Subcontractor arising out of this Subcontract shall be resolved by

submission of the same to GAMA, Inc., for resolution by binding

arbitration according to GAMA's Rules of Arbitration. In so

agreeing the parties expressly waive their right to a jury trial,

if any, on these issues and further agree that the award of the

arbitrator shall be final and binding upon them as though rendered

by a court of law and shall be enforceable in any court having

jurisdiction over the same.

 

THIS SUBCONTRACT IS ACKNOWLEDGED AND EXECUTED AS OF THE DATE SET

FORTH ABOVE:

 

____________________________    ____________________________

SUBCONTRACTOR                   CONTRACTOR

 

By: _______________________ By: ________________________

 

Titles: ____________________ Title: _____________________

 


Click filename below to access file

Subcontract.doc




Business Forms Privacy Policy Also See Terms of Service.